As a part of our work trip to the Lethbridge region, Solar Plantation completed this 92KW solar project in summer 2016. This one was one of the three projects completed. Schletter Canada managed to manufacture and ship all materials before the originally scheduled date. At this site, we managed to install 75 meter long rows of racking, all in one long line. FS System racking allowed for adjustments to ensure PV modules alignment. All projects on this trip were completed ahead of schedule.

Solar Plantation scope of work included: soil sampling, engineering, site layout, pile-driving, and racking installation. The project is completed under the Alberta Growing Forward program, ENMAX funding and in a partnership with Solar Optix.